For the extension of the Bordier hut, weight management is a priority as every construction material must be transported by helicopter.

Location
St. Niklaus, VS
Architect
Lacroix Chessex
Client
CAS section Genève
Time
2026
Result
2nd place

Project Story

For the extension of the Bordier hut, weight management is a priority as every construction material must be transported by helicopter. Following measures reduce the amount of material needed to be transported:

  • The floor structure is delivered without ballast. Fill material available on site is crushed and reused as ballast to meet acoustic requirements. Electrical routing is also integrated into this layer.
  • The walls and floors of the existing extension are reused to insulate the basement from the surrounding concrete walls and foundation slab.
  • Concrete for the foundation slab and basement is produced using aggregates available on site, obtained by crushing the slab of the existing extension as well as existing fill material.